WATER AND WATER RELATED
RATES, CHARGES AND FEES
FY 2022 SUMMARY
NEW SMYRNA BEACH UTILITIES
NARRATIVE
This Rates, Charges and Fees Summary provides a general overview of New Smyrna Beach
Utilities’ Rates and Resolutions. For any additional information refer to the Rates and/or
Resolution documents
3
NEW SMYRNA BEACH UTILITIES
TABLE OF CONTENTS
I. CAPITOL CONNECTION FEES PAGE NO.
Capitol Connection Fee Charges - Potable Water ...............................................................4
Capitol Connection Fee Charges - Irrigation Water ............................................................6
Capitol Connection Fee Charges - Wastewater ...................................................................7
Capitol Connection Fee Charges - Reclaimed Water ..........................................................8
Capitol Connection Fee Charges - Notes ............................................................................9
Financing Capitol Connection Fees, Meter Setting Fees, Tap-in Fees and Cut-in Fees 10
II. WATER
Potable Water Rate Schedule .............................................................................................11
Charges for Water Meter Setting Installations ...................................................................15
Water Main Extension Policy ............................................................................................17
III. WASTEWATER
Wastewater Tap-in Installation Charges ............................................................................22
Wastewater Rate Schedule .................................................................................................23
Wastewater Main Extension Policy ...................................................................................25
IV. RECLAIMED
Reclaimed Water Rate Schedule ........................................................................................30
Reclaimed Water Meter Setting Charges ...........................................................................32
Reclaimed Water Backflow Prevention Charges ...............................................................33
Reclaimed Water Main Extension Policy ..........................................................................34
Reclaimed Water Irrigation Policy ....................................................................................39
V. CUSTOMER DEPOSIT ....................................................................................................40
VI. SERVICE FEES SCHEDULE ...........................................................................................46
4
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CAPITAL CONNECTION FEE CHARGES - POTABLE WATER
The Potable Water Capital Connection Fee charge is established based on meter
size and number of meters requested. The Capital Connection Fee charge per meter
size for Potable Water is as listed in the TABLE below:
TABLE POTABLE WATER
Meter Size (inch)
Capital
Connection Fee ($)
5/8"
$1,485
1"
$3,713
1-1/2"
$7,425
2"
$11,880
3"
$22,275
4"
$37,125
6"
$74,250
8"
$118,800
10"
$170,775
12"
$319,275
Notes:
1. For Commercial projects:
a. The meter size (and accompanying backflow device) must match the
size of supply plumbing to the building.
b. The applicant must provide signed and sealed plumbing plans prior
to acceptance of capital connection fees for review by
The New Smyrna Beach Utilities Engineering Department.
c. The New Smyrna Beach Utilities Engineering Department may
accept “a meter size” smaller than the proposed plumbing, provided
signed and sealed engineering calculations by a MEP Engineer are
provided for review and acceptance. (For Example: a 4” plumbing
size would have an opportunity provided by calculation by
landowner/developer for a 3” meter, but no smaller.)
d. Meter and backflow devices must be same size.
e. Master meters are only permitted for buildings three stories or more
and/or or as determined feasible by the Utility Commission
Engineering Department. System pressure diminishes above the 2
nd
floor. Special equipment (by developer/owner) may be required for
floors 3 and above.
EFFECTIVE: June 1, 2021
5
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CAPITAL CONNECTION FEE CHARGES - POTABLE WATER (Cont.)
Notes: (Cont.)
2. The New Smyrna Beach Utilities only offers the meter sizes listed above.
3. The fees listed above are priced on a per meter basis 4. The fees will not be
applied to existing meters.
5. Fees will only apply to each new meter whether residential, commercial,
industrial, common area, expansion, upsizing, etc.
6. A credit will be given for the existing meter when that meter is replaced
with a larger meter.
7. The Capital Connection Fee does not include other fees.
EFFECTIVE: June 1, 2021
6
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CAPITAL CONNECTION FEE CHARGES - IRRIGATION WATER
The Irrigation Water Capital Connection Fee charge is established based on meter
size and number of meters requested. The Capital Connection Fee charge per meter
size for Irrigation water is as listed in the TABLE below:
TABLE IRRIGATION WATER
Meter Size (inch)
Capital
Connection Fee ($)
5/8"
$2,970
1"
$7,425
1-1/2"
$14,850
2"
$23,760
3"
$44,550
4"
$74,250
6"
$148,500
8"
$237,600
10"
$341,550
12"
$638,550
Notes:
1. Irrigation meters are used primarily for irrigation purposes and are generally
the second meter for an account.
2. An independent Irrigation meter is possible without a Potable Water meter.
3. Irrigation meters can also be used to serve common areas in both residential
and/or commercial developments, respectively.
4. There are no Wastewater connections associated with an irrigation meter.
5. The New Smyrna Beach Utilities only offers the meter sizes listed above.
6. The fees listed above are priced on a per meter basis.
7. The fees will not be applied to existing meters.
8. Fees will only apply to each new meter whether residential, commercial,
industrial, common area, expansion, upsizing, etc.
9. A credit will be given for the existing meter when that meter is replaced
with a larger meter.
10. The Capital Connection Fee does not include other fees.
EFFECTIVE: June 1, 2021
7
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CAPITAL CONNECTION FEE CHARGES - WASTEWATER
The Wastewater Capital Connection Fee charge is established based on meter size
and number of meters requested. The Capital Connection Fee charge per meter size
for Wastewater is as listed in the TABLE below:
TABLE WASTEWATER
Potable Water
Meter Size (inch)
Capital
Connection Fee ($)
5/8"
$1,445
1"
$3,613
1-1/2"
$7,225
2"
$11,560
3"
$21,675
4"
$36,125
6"
$72,250
8"
$115,600
10"
$166,175
12"
$310,675
Notes:
1. Regardless of the Potable water meter size and corresponding Wastewater
Capital Connection Fee, the smallest residential Wastewater connection
(lateral) shall be four (4) inches.
2. Regardless of the Potable water meter size and the corresponding
Wastewater Capital Connection Fee, the smallest commercial Wastewater
connection (lateral) shall be six (6) inches.
3. The Wastewater Capital Connection Fee shall be based on the Potable water
meter size service for the proposed unit. (Unit refers to single residential
home, separate commercial services, including lease and purchase space,
etc.)
4. The New Smyrna Beach Utilities only offers the meter sizes listed above.
5. The fees listed above are priced on a per meter basis.
6. The fees will not be applied to existing Wastewater connections.
7. Fees will only apply to each new Wastewater connection, whether
residential, commercial, industrial, common area, expansion, upsizing, etc.
8. A credit will be given for the existing meter when that meter is replaced
with a larger meter.
9. The Capital Connection Fee does not include other fees.
EFFECTIVE: June 1, 2021
8
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CAPITAL CONNECTION FEE CHARGES - RECLAIMED WATER
The Reclaimed Water Capital Connection Fee charge is established based on meter
size and number of meters requested. The Capital Connection Fee charge per meter
size for Reclaimed Water is as listed on the TABLE below:
TABLE RECLAIMED WATER
Meter Size (inch)
Capital
Connection Fee ($)
3/4"
$635
1"
$1,058
1-1/2"
$2,117
2"
$3,387
3"
$6,350
4"
$10,583
6"
$21,167
8"
$33,867
10"
$48,683
12"
$91,017
Notes:
1. The Reclaimed Water Capital Connection Fee shall be based on the
Reclaimed Water meter size serving the proposed unit. (Unit refers to single
residential home, separate commercial services, including lease and
purchase space.)
2. The New Smyrna Beach Utilities only offers the meter sizes listed above.
3. The fees listed above are priced on a per meter basis.
4. The fees will not be applied to existing Reclaimed Water meters.
5. Fees will only apply to each new Reclaimed Water connection, whether
residential, commercial, industrial, common area, expansion, upsizing, etc.
6. A credit will be given for the existing meter when that meter is replaced
with a larger meter.
7. The Capital Connection Fee does not include other fees.
EFFECTIVE: June 1, 2021
9
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CAPITAL CONNECTION FEE CHARGES - NOTES
1. A 5/8” potable water meter will be considered one Equivalent Residential Unit
(ERU) which represents a nominal usage (or level of service) of 200 gallons per
day for potable water, as determined by utilizing historical customer account
records and water sales for the New Smyrna Beach Utilities ’s system.
2. A 3/4” reclaimed meter will be considered one Equivalent Residential Unit
(ERU) which represents a nominal usage (or level of service) of 500 gallons per
day for reclaimed water, as determined by utilizing historical customer account
records and water sales for the New Smyrna Beach Utilities ’s system.
3. A 5/8” irrigation water meter will be considered one Equivalent Residential
Unit (ERU) which represents a nominal usage (or level of service) of 400
gallons per day for potable water, as determined by utilizing historical customer
account records and water sales for the New Smyrna Beach Utilities ’s system.
4. The aforementioned capital connection fee charges constitute potable water,
irrigation water, wastewater and reclaimed water capital connection fee charges
only and such charges shall be paid before any connection will be made, and
only upon determination by the New Smyrna Beach Utilities that existing water
facilities are available to which the connection is made.
5. Payment of the capital connection fee charges must be made to the New Smyrna
Beach Utilities in advance of issuance of building permits within our service
area.
6. The aforementioned charges as detailed above apply to all applications for
service approved subsequent to the effective date of Resolution No. 2021-01
and because capital connection fee charges cannot be held in abeyance
indefinitely, the application for water, wastewater, irrigation water and
reclaimed water service shall be restricted to be in effect ninety (90) days or as
long as the original building permit is valid, whichever is longer. In the event
the service connection has not been made prior to the aforementioned
restriction, water, wastewater, irrigation water and reclaimed water capital
connection fee charges will be subject to revision to the successor fee schedule.
EFFECTIVE: June 1, 2021
10
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
FINANCING CAPITAL CONNECTION FEES, METER SETTING FEES,
TAP-IN FEES AND CUT-IN FEES
Upon certification by New Smyrna Beach Utilities Engineering Department that
the service connection has not been made for the specific application for service
and the applicant has withdrawn the application for service (in writing), the Water,
Irrigation Water, Wastewater and Reclaimed Water Capital Connection Fee
charges that have been paid will be subject to refund without interest.
Such Water, Irrigation Water, Wastewater and Reclaimed Water Capital
Connection Fee charges are in addition to meter setting installation charges, line
extension contributions, or other charges and fees as may be appropriate for
services rendered.
Financing of payment of Water, Irrigation Water, Wastewater and Reclaimed
Water Capital Connection Fees, meter setting charges, tap-in fees and cut-in
charges will be available pursuant to the terms and conditions listed below:
1. Financing is made available to all individual residential customer
applicants.
2. A 12-month or 24-month financing period will be utilized.
3. An annual interest rate of 2% above prime shall be used.
4. The customer must execute an agreement which states the utilities
applicable (Water, Irrigation Water, Wastewater and/or Reclaimed Water)
will be terminated if the customer is in default of payments. All payments
previously made are non-refundable.
5. All payments must be accelerated and are due in full prior to transfer of
ownership of the property.
6. A non-refundable administrative fee of $50.00 must be paid at the time of
application in order to reimburse the New Smyrna Beach Utilities for
services required to administer the records and financing process.
EFFECTIVE: June 1, 2021
11
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
POTABLE WATER RATE SCHEDULE
Residential Service Single Family:
Meter Size
(Inches)
Base
Facility Charge
Total Monthly Bill
5/8"
$13.86
$ 13.86 + Gallonage Charge
1"
$34.66
$ 34.66 + Gallonage Charge
1-1/2"
$69.32
$ 69.32 + Gallonage Charge
2"
$110.91
$ 110.91 + Gallonage Charge
3"
$207.95
$ 207.95 + Gallonage Charge
4"
$346.59
$ 346.59 + Gallonage Charge
6"
$693.18
$ 693.18 + Gallonage Charge
8"
$1,109.08
$1,109.08 + Gallonage Charge
10"
$1,594.30
$1,594.30 + Gallonage Charge
Gallonage Charge/1,000 Gallons
Block 1
Block 2
Block 3
Block 4
$1.11
$1.48
$2.33
$2.77
Monthly Rate Blocks (Gallons)
Meter Size
Block 1
Block 2
Block 3
Block 4
5/8"
0-2,999
3,000-5,999
6,000-15,000
Above 15,000
1"
0-5,999
6,000-13,999
14,000-38,000
Above 38,000
1-1/2"
0-10,999
11,000-25,999
26,000-75,000
Above 75,000
2"
0-16,999
17,000-40,999
41,000-120,000
Above 120,000
3"
0-30,999
31,000-75,999
76,000-225,000
Above 225,000
4"
0-50,999
51,000-125,999
126,000-375,000
Above 375,000
6"
0-100,999
101,000-250,999
251,000-750,000
Above 750,000
8"
0-160,999
161,000-400,999
401,000-1,200,000
Above 1,200,000
10"
0-230,999
231,000-575,999
576,000-1,725,000
Above 1,725,000
EFFECTIVE: October 1, 2021
12
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
POTABLE WATER RATE SCHEDULE (Cont.)
Irrigation/Supplemental Service:
Meter Size
(Inches)
Base
Facility Charge
Total Monthly Bill
5/8"
$18.03
$ 18.03 + Gallonage Charge
1"
$45.07
$ 45.07 + Gallonage Charge
1-1/2"
$90.12
$ 90.12 + Gallonage Charge
2"
$144.18
$ 144.18 + Gallonage Charge
3"
$270.34
$ 270.34 + Gallonage Charge
4"
$450.57
$ 450.57 + Gallonage Charge
6"
$901.13
$ 901.13 + Gallonage Charge
8"
$1,441.80
$1,441.80 + Gallonage Charge
10"
$2,072.60
$2,072.60 + Gallonage Charge
Gallonage Charge/1,000 Gallons
Block 1
Block 2
Block 3
Block 4
$2.28
$3.05
$4.80
$5.71
Monthly Rate Blocks (Gallons)
Meter Size
Block 1
Block 2
Block 3
Block 4
5/8"
0-2,999
3,000-5,999
6,000-15,000
Above 15,000
1"
0-5,999
6,000-13,999
14,000-38,000
Above 38,000
1-1/2"
0-10,999
11,000-25,999
26,000-75,000
Above 75,000
2"
0-16,999
17,000-40,999
41,000-120,000
Above 120,000
3"
0-30,999
31,000-75,999
76,000-225,000
Above 225,000
4"
0-50,999
51,000-125,999
126,000-375,000
Above 375,000
6"
0-100,999
101,000-250,999
251,000-750,000
Above 750,000
8"
0-160,999
161,00-400,999
401,000-1,200,000
Above 1,200,000
10"
0-230,999
231,000-575,999
576,000-1,725,000
Above 1,725,000
EFFECTIVE: October 1, 2021
13
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
POTABLE WATER RATE SCHEDULE (Cont.)
Non-Residential Service:
Meter Size
(Inches)
Base
Facility Charge
Total Monthly Bill
5/8"
$13.86
$ 13.86 + Gallonage Charge
1"
$34.66
$ 34.66 + Gallonage Charge
1-1/2"
$69.32
$ 69.32 + Gallonage Charge
2"
$110.91
$ 110.91 + Gallonage Charge
3"
$207.95
$ 207.95 + Gallonage Charge
4"
$346.59
$ 346.59 + Gallonage Charge
6"
$693.18
$ 693.18 + Gallonage Charge
8"
$1,109.08
$1,109.08 + Gallonage Charge
10"
12”
$1,594.30
$2,148.84
$1,594.30 + Gallonage Charge
$2,148.84 + Gallonage Charge
Gallonage Charge/1,000 Gallons
Meter Size
Block 1
Block 2
All Meter Sizes
$1.83
$2.44
Monthly Rate Blocks (Gallons)
Meter Size
Block 1
Block 2
5/8"
0 - 7,000
Above 7,000
1"
0 - 18,000
Above 18,000
1-1/2"
0 - 35,000
Above 35,000
2"
0 - 56,000
Above 56,000
3"
0 - 105,000
Above 105,000
4"
0 - 175,000
Above 175,000
6"
0 - 350,000
Above 350,000
8"
0 - 560,000
Above 560,000
10"
0 - 805,000
Above 805,000
12"
0 1,087,000
Above 1,087,000
EFFECTIVE: October 1, 2021
14
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
POTABLE WATER RATE SCHEDULE (Cont.)
Multi-Family Buildings/Developments:
Billing
Account
Base
Facility
Charge
Gallonage
Charge per KG
All Usage
Total Monthly Bill
Each Unit
$13.86
$-0-
$13.86
Master Meter
$13.86
$1.31
$13.86 + Gallonage
Charge
Connection fees, deposits and other such fees imposed by the New Smyrna Beach
Utilities shall not be affected by the provisions of this rate schedule.
Charges for meter sizes not listed above shall be set by the New Smyrna Beach Utilities
on a case-by-case basis, calculated to reflect any incremental sizes in accordance with
the provisions of this rate schedule.
EFFECTIVE: October 1, 2021
15
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CHARGES FOR WATER METER SETTING INSTALLATIONS
Connection facilities for Water service will be installed by the New Smyrna Beach
Utilities, the cost of which is to be paid from the Water Setting Installation Charge set
out herein, which will include pipe from the water main to the property line, fittings and
other material related to a normal connection and a water meter, whenever the applicant
shall have paid therefore the required deposit for the water service, line extension
contributions, water connection fee charges, or other charges and fees as may be
appropriate for service rendered. The Water Meter Setting Installation Charges shall be
as follows:
Water Meter
Size (Inches)
Water Setting
Installation Charge
Supplemental Meter
Setting Installation
Charge
5/8
$ 400
$ 300
1
$ 450
$ 350
1-1/2
$ 850
$ 750
2
$ 950
$ 850
3
$6,000
$5,400
4
$7,000
$6,350
All Water Meter Setting Installation Charges of 1-1/2 or larger that require a street
crossing or long service (long side service) will be determined by the New Smyrna Beach
Utilities s Engineering Department and based on the recovery of cost of such installation.
Water Meter Setting Installation Charges for all connections over 4" will be determined
by the New Smyrna Beach Utilities Engineering Department and based on the recovery
cost of such installation.
To qualify as a supplemental meter setting, meters shall meet all the following conditions:
1. The customer shall have an existing domestic meter.
2. The supplemental meter requested is equal to or smaller than the existing
domestic meter.
3. The New Smyrna Beach Utilities taps the existing domestic service
between the meter and main, but no tap is made on the same water
main.
EFFECTIVE: October 1, 2021
16
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CHARGES FOR WATER METER SETTING INSTALLATIONS (Cont.)
Residential subdivisions, with five or more building lots, that have the water main,
service line to the property line, fittings and other material relating to a normal connection
paid for and installed by the same person or entity and in accordance with the New
Smyrna Beach Utilities specifications; the applicant as herein defined shall receive a
refund of $260.00 toward the 5/8" Water Meter Setting Installation Charge.
Should the installation not meet the minimum construction standards set by the New
Smyrna Beach Utilities at the time of meter installation, no refund shall be given to the
applicant. The applicant is defined as the person or entity who has made actual
application to the New Smyrna Beach Utilities for 5/8" water service and who has paid
all 5/8" water meter setting installation charges.
Such Water Meter Setting Installation Charges are in addition to Water Capital
Connection Fees, line extension contributions, or other charges and fees which may be
appropriate for service rendered.
EFFECTIVE: October 1, 2021
17
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WATER MAIN EXTENSION POLICY
Applications for an extension of the New Smyrna Beach Utilities water system shall be
in writing stating the location, beginning and termination thereof, with plans and
specifications in triplicate attached where such plans and specifications are required.
Such written request shall be submitted to the Director of Engineering, approved by the
Director of Engineering and all terms and conditions relating to said extension shall be
made and executed by and between the applicant property owner and/or contractor and
the New Smyrna Beach Utilities.
No unauthorized person, without prior written consent of the New Smyrna Beach
Utilities, may tap any pipe or main belonging to the New Smyrna Beach Utilities. All
unauthorized connections shall be subject to discontinuance until full payment is made
for such service, including administrative costs, testing, etc.
All pipes, conduits or other component parts of service installed in or upon the premises
of a customer shall conform to New Smyrna Beach Utilities standards of type, quality,
quantity and regulations regarding installation. All on-site facilities must be maintained
by the applicant according to New Smyrna Beach Utilities standards. Unauthorized
alteration or modification of an on-site utility service interconnection may result in
immediate termination of the affected service and repair or restoration at the applicant's
cost.
Fire service extensions apply solely for commercial, industrial and/or multi-family
customers. The New Smyrna Beach Utilities provides adequate fire protection facilities
for typical residential service and will not pay for the increment of any oversized pipe
from domestic flows to fire service flows for a commercial, industrial or multi-family
installation.
Prior to New Smyrna Beach Utilities approval of the applicant's water service plans, the
applicant must enter into a Developer's Agreement which shall be binding upon the
applicant and its successors and assigns. Developer's Agreements may not be assigned to
subdivision parcels and/or lots.
The New Smyrna Beach Utilities requires contributions-in-aid-of-construction,
preferably through the installation of water transmission facilities by the applicant
desiring system extension with title to such facilities being transferred to the New Smyrna
Beach Utilities when the installation has been completed. Cash payment of water system
Capital Connection Fees by the applicant represents a condition precedent to the
execution of permit applications to the Department of Environmental Protection for the
construction of water system extensions.
EFFECTIVE: October 1, 2021
18
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WATER MAIN EXTENSION POLICY (Cont.)
Each applicant shall be responsible for design, installation, inspection and testing of the
complete water distribution system (water mains, valves, fittings, services, hydrants and
all appurtenances as shown upon the approved design plans for such water distribution
system) located in the street or streets adjoining or within the boundaries of the applicant's
property (within the right-of-way or easement). The applicant shall be responsible for
the above and shall dedicate the above at no cost to the New Smyrna Beach Utilities.
The design of water facilities prepared by a registered Professional Civil Engineer shall
be recognized by the New Smyrna Beach Utilities, subject to the approval of the Director
of Engineering.
As a prerequisite to the construction of any water system proposed to be connected to the
New Smyrna Beach Utilities water distribution system, the applicant shall grant all
easements and rights-of-way, without cost, as may be necessary.
The New Smyrna Beach Utilities 's representative shall inspect all the water facilities
installed which are proposed to be transferred to the New Smyrna Beach Utilities
ownership. In addition, the New Smyrna Beach Utilities 's representative shall be present
at all testing of the component parts of the water distribution system. The results of said
testing shall be certified by the engineer of record. The Director of Engineering or their
representative shall be notified three (3) days prior to testing.
Water facilities constructed prior to interconnection with the New Smyrna Beach Utilities
existing facilities shall be conveyed to the New Smyrna Beach Utilities via Bill of Sale
which shall be free of all liens and encumbrances. The New Smyrna Beach Utilities will
not accept transfer of consumer lines, plumber lines or consumers installation located on
the discharge side of the water meter or on the customer side of the point of delivery of
service. Said facilities will remain the maintenance responsibility of the applicant or
subsequent customers. The New Smyrna Beach Utilities will not accept title to any
component part of the water system constructed by the applicant until the Director of
Engineering has approved the construction of said lines, verified the inspection of the
construction and accepted the tests associated with the construction and disinfection of
such facilities. The applicant must keep accurate cost records of all applicable water
distribution facilities and must submit these with the Bill of Sale.
EFFECTIVE: October 1, 2021
19
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WATER MAIN EXTENSION POLICY (Cont.)
Residential off-site water system services in undeveloped areas include:
1. Temporary extensions less than 6-inches in diameter may be permitted on
a case-by-case basis based on public necessity. No New Smyrna Beach
Utilities participation, credits or other customer tie-ins will be allowed.
Fire protection is not included, and applicant must pay all prevailing rates,
fees and charges and is totally responsible for all costs associated with this
extension, including looping the system which is a requirement.
2. 6-inch Water Main Extensions - The main extensions from the New
Smyrna Beach Utilities system to the applicant’s on-site facilities is
required to be paid by the applicant.
3. 8-inch Diameter or Larger Water Main Extensions - If the applicant
requires a 6-inch water main and oversizing is required, the New Smyrna
Beach Utilities may, in order to promote a project also needed for other
purposes, pay for the material cost of the differential between a 6-inch and
the larger diameter main.
Residential off-site water system services in developed areas include:
1. The New Smyrna Beach Utilities shall provide three options for service
for developed areas. Those options include:
Customer Payment
Area Development Agreement
Water Special District (Assessment, Taxing or Otherwise)
2. The New Smyrna Beach Utilities shall construct the extension upon
collection of Capital Connection Fees and extension costs from one
hundred percent (100%) of the impacted customers upon said extension.
Each extension will be reviewed for feasibility based on prudent
engineering standards.
The remainder of the policies for individual customers within undeveloped areas include:
1. An area development agreement would be considered the same as any
other Developer's Agreement.
EFFECTIVE: October 1, 2021
20
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WATER MAIN EXTENSION POLICY (Cont.)
2. Special districts, special assessments or special taxing may be instituted
within the New Smyrna Beach Utilities service area. These shall be
considered as a development and on-site and off-site costs shall be
required like any other applicant in an undeveloped area. The off-site
improvements and extensions shall be handled like those for water
facilities.
Commercial off-site water system services in undeveloped areas include:
1. Water main requirements, except for fire service, shall be the same as for
residential service.
Commercial off-site water system services in developed areas include:
1. Water main requirements, except for fire service, shall be the same as for
residential service in developed areas.
Hydraulic share for water mains is defined as follows:
1. 6" - 270 ERU's
2. 8" - 600 ERU's
3. 10" - 1,000 ERU's
4. 12" - 1,700 ERU's
5. 16" - 3,400 ERU's
Other calculations may be accepted by the Director of Engineering, if performed and
properly sealed by a Florida Licensed Professional Engineer, using constants, and rates
accepted by the Director of Engineering.
Utility inspection fees shall be $50.00 per water ERU.
The New Smyrna Beach Utilities requires in many cases, in addition to the contribution
provisions set forth herein, construction by the developer to provide for off-site extension
of water necessary to connect the applicant’s property with the then terminus of the water
facilities adequate in size to provide service as deemed appropriate by the Director of
Engineering.
Additional Infrastructure Needs - Any New Smyrna Beach Utilities utility infrastructure
needs will be considered separately.
EFFECTIVE: October 1, 2021
21
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WATER MAIN EXTENSION POLICY (Cont.)
Financing of payment of water extensions is available pursuant to the terms and
conditions listed below:
1. Financing would be available to all individual residential customer
applicants.
2. A 12-month or 24-month financing period will be utilized.
3. An annual interest rate of 2% above prime shall be used.
4. The customer must execute an agreement which states water will be
terminated if the customer is in default of payments. All payments
previously made are non-refundable.
5. All payments must be accelerated and due in full prior to transfer of
ownership of the property.
6. A non-refundable administrative fee of $50.00 must be paid at the time
of application in order to reimburse the New Smyrna Beach Utilities for
services required to administer the records and financing process.
EFFECTIVE: October 1, 2021
22
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WASTEWATER TAP-IN INSTALLATION CHARGE
The Wastewater Tap-in Installation Charge shall be applied to all Wastewater service
installations if the applicant requires a separate wastewater tap-in because:
a. No previous tap-in has been indicated by the Commission's record
drawings;
b. The applicant requested a tap-in location different from the existing tap-
in location;
c. The existing tap-in was damaged by the applicant.
Based on the criteria above, the Wastewater Tap-in Installation Charge shall be $350.00
for a standard installation.
If any installation is determined by the Engineering Department to require substantially
more manhours, equipment, or materials, then the Wastewater Tap-in Installation Charge
shall be individually calculated and assessed. It is the applicant’s responsibility to expose
the wastewater main for tapping and burying the main after the tap is made. It is the
applicants responsibility to obtain any required permits to perform this work.
Such Wastewater Tap-in Installation Charge is in addition to Wastewater Capital
Connection Fees, line extension contributions, or other charges or fees which may be
appropriate for services rendered.
EFFECTIVE: October 1, 2021
23
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WASTEWATER RATE SCHEDULE
Residential Service Single Family:
Meter Size
(Inches)
Base
Facility Charge
Total Monthly Bill
5/8"
$19.54
$ 19.54 + Gallonage Charge
1"
$48.87
$ 48.87 + Gallonage Charge
1-1/2"
$97.72
$ 97.72 + Gallonage Charge
2"
$156.37
$ 156.37 + Gallonage Charge
3"
$293.18
$ 293.18 + Gallonage Charge
4"
$488.63
$ 488.63 + Gallonage Charge
6"
$977.26
$ 977.26 + Gallonage Charge
8"
$1,563.61
$1,563.61 + Gallonage Charge
10"
$2,247.69
$2,247.69 + Gallonage Charge
Gallonage Charge/1,000 Gallons
All Meter Sizes
$4.27
EFFECTIVE: October 1, 2021
24
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WASTEWATER RATE SCHEDULE (Cont.)
Non-Residential Service:
Meter Size
(Inches)
Base
Facility Charge
Total Monthly Bill
5/8”
$19.54
$ 19.54 + Gallonage Charge
1"
$48.87
$ 48.87 + Gallonage Charge
1-1/2"
$97.72
$ 97.72 + Gallonage Charge
2"
$156.37
$ 156.37 + Gallonage Charge
3"
$293.18
$ 293.18 + Gallonage Charge
4"
$488.63
$ 488.63 + Gallonage Charge
6"
$977.26
$ 977.26 + Gallonage Charge
8"
$1,563.61
$1,563.61 + Gallonage Charge
10"
$2,247.69
$2,247.69 + Gallonage Charge
Gallonage Charge/1,000 Gallons
All Meter Sizes
$5.50
Multi-Family:
Billing
Account
Base
Facility
Charge
Gallonage
Charge
Per KG
All Usage
Total Monthly Bill
Each Unit
$19.54
$ -0-
$19.54
Master Meter
$19.54
$3.41
$19.54 + Gallonage
Charge
Connection fees, deposits and other such fees imposed by the New Smyrna Beach
Utilities shall not be affected by the provisions of this rate schedule.
Charges for meter sizes not listed above shall be set by the New Smyrna Beach Utilities
on a case-by-case basis, calculated to reflect any incremental sizes in accordance with
the provisions of this rate schedule.
Residential (single family) customers that do not receive metered water service shall pay
a monthly fixed wastewater charge as follows: $40.89.
EFFECTIVE: October 1, 2021
25
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WASTEWATER MAIN EXTENSION POLICY
Applications for an extension of the New Smyrna Beach Utilities 's wastewater system
shall be in writing stating the location, beginning and termination thereof, with plans and
specifications in triplicate attached where such plans and specifications are required.
Such written request shall be submitted to the Director of Engineering, approved by the
Director of Engineering and all terms and conditions relating to said extension shall be
made and executed by and between the applicant property owner and/or contractor and
the New Smyrna Beach Utilities.
No unauthorized person, without prior written consent of the New Smyrna Beach Utilities
may tap any pipe or main belonging to the New Smyrna Beach Utilities. All unauthorized
connections shall be subject to discontinuance until full payment is made for such service,
including administrative costs, testing, etc.
All pipes, conduits or other component parts of service installed in or upon the premises
of a customer shall conform to New Smyrna Beach Utilities standards of type, quality,
quantity and regulations regarding installation. All on-site facilities must be maintained
by applicant according to New Smyrna Beach Utilities standards. Unauthorized alteration
or modification of an on-site utility service interconnection may result in immediate
termination of the affected service and repair or restoration at the applicant's cost.
Prior to New Smyrna Beach Utilities approval of the applicant's wastewater service plans,
the applicant must enter into a Developer's Agreement which shall be binding upon the
applicant and its successors and assigns. Developer's Agreements may not be assigned to
subdivision parcels and/or lots.
The New Smyrna Beach Utilities requires contributions-in-aid-of-construction,
preferably through the installation of wastewater collection facilities by the applicant
desiring system extension with title to such facilities being transferred to the New Smyrna
Beach Utilities when the installation has been completed. Cash payment of wastewater
system Capital Connection Fees by the applicant represents a condition precedent to the
execution of permit applications to the Department of Environmental Protection for the
construction of wastewater system extensions.
Each applicant shall be responsible for design, installation, inspection and testing of the
complete wastewater collection system (collection mains, laterals to the point of clean-
out within the right-of-way or easement, force mains, lift or pumping stations, including
the site for the same, and all appurtenances as shown upon the approved design plans for
such wastewater collection system) located in the street or streets adjoining or within the
boundaries of the applicant's property (within the right-of-way or easement). The
applicant shall be responsible for the above and shall dedicate the above at no cost to the
New Smyrna Beach Utilities.
EFFECTIVE: October 1, 2021
26
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WASTEWATER MAIN EXTENSION POLICY (Cont.)
The design of wastewater facilities prepared by a registered Professional Civil Engineer
shall be recognized by the New Smyrna Beach Utilities subject to the approval of the
Director of Engineering.
As a prerequisite to the construction of any wastewater system proposed to be connected
to the New Smyrna Beach Utilities wastewater collection system, the applicant shall grant
all easements and rights-of-way, without cost, as may be necessary.
The New Smyrna Beach Utilities representative shall inspect the installation of all
wastewater facilities installed which are proposed to be transferred to the New Smyrna
Beach Utilities ownership. In addition, the New Smyrna Beach Utilities representative
shall be present at all testing of the component parts of the wastewater collection system.
The results of said testing shall be certified by the engineer of record. The Director of
Engineering or their representative shall be notified three (3) days prior to testing.
Wastewater facilities constructed prior to interconnection with the New Smyrna Beach
Utilities existing facilities shall be conveyed to the New Smyrna Beach Utilities via Bill
of Sale which shall be free of all liens and encumbrances. The New Smyrna Beach
Utilities will not accept transfer of consumer lines, plumber lines or consumers
installation located on the discharge side of the water meter or on the customer side of
the point of delivery of service. Said facilities will remain the maintenance responsibility
of the applicant or subsequent customers. The New Smyrna Beach Utilities will not
accept title to any component part of the wastewater system constructed by the applicant
until the Director of Engineering has approved the construction of said lines, verified the
inspection of the construction and accepted the tests associated with the construction and
disinfection of such facilities. The applicant must keep accurate cost records of all
applicable pollution control collection facilities and must submit these with the Bill of
Sale.
Residential off-site wastewater collection system services in undeveloped areas include:
1. 100 GPM lift stations are the minimum size lift stations for off-site use
within the New Smyrna Beach Utilities service area. The 100 GPM
capacity is necessary for scour velocities within the 4-inch force mains
from such facilities, and thereby shall be minimum.
2. Lift stations greater than 100 GPM must be paid for completely by the
applicant. The New Smyrna Beach Utilities reserves the right to oversize
the lift station paying for the incremental material cost for oversizing.
EFFECTIVE: October 1, 2021
27
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WASTEWATER MAIN EXTENSION POLICY (Cont.)
3. 4-inch force mains shall be paid for by the applicant from the point of
connection to the New Smyrna Beach Utilities to the on-site facilities.
4. 6-inch force mains or larger that are extensions of New Smyrna Beach
Utilities facilities requiring oversizing may at the Commission’s
discretion be paid for by the New Smyrna Beach Utilities.
5. For 6-inch or larger system extensions the New Smyrna Beach Utilities
may credit some portion of the cost if it is in the Commission’s interest to
promote the extension of this line. The applicant is responsible for the
remainder of the cost of the force main extension. The New Smyrna Beach
Utilities reserves the right to oversize such facilities and pay for said
oversizing in accordance with New Smyrna Beach Utilities policies.
Residential off-site water system services in developed areas include:
1. The New Smyrna Beach Utilities shall provide three options for service
for developed areas. Those options include:
Customer Payment
Area Development Agreement
Water Special District (Assessment, Taxing or Otherwise)
2. The New Smyrna Beach Utilities shall construct the extension upon
collection of capital connection fees and extension costs from one hundred
percent (100%) of those customers upon said extension. Each extension
will be reviewed for feasibility based on prudent engineering standards.
3. The customer shall pay the cost for all line extensions to the wastewater
system. Such extensions shall be in accordance with the Commission’s
policies. Road and/or drainage restoration costs shall be borne by the
applicant, City and/or County as applicable.
The remainder of the policies for individual customers within undeveloped
areas apply.
4. An area development agreement would be considered the same as any
other Developer's Agreement.
EFFECTIVE: October 1, 2021
28
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WASTEWATER MAIN EXTENSION POLICY (Cont.)
5. Special districts, special assessments or special taxing may be instituted
within the New Smyrna Beach Utilities service area. These shall be
considered as a development and on-site and off-site costs shall be
required like any other applicant in an undeveloped area. The off-site
improvements and extensions shall be handled like those for wastewater
facilities.
Commercial off-site wastewater system services in undeveloped areas include:
1. Wastewater facilities extensions shall be in accordance with special
provisions of utility standards and shall be complied with in their entirety;
otherwise, the requirements shall be the same as for residential service.
Commercial off-site wastewater system services in developed areas include:
1. Extensions shall be in accordance with special provisions of utility
standards and shall be complied with in their entirety; otherwise, the
requirements shall be the same as for residential service in developed
areas.
Hydraulic share for wastewater is defined as follows:
1. Wastewater Pumping Stations - 1 GPM Capacity per ERU
2. Wastewater Force Mains
4" - 120 ERU's
6" - 320 ERU's
8" - 700 ERU's
10" - 1,200 ERU's
12" - 2,000 ERU's
3. Wastewater Gravity Interceptors
10" - 600 ERU's
12" - 1,000 ERU's
15" - 1,800 ERU's
18" - 3,300 ERU's
Other calculations may be accepted by the Director of Engineering, if performed
and properly sealed by a Florida Licenses Professional Engineer, using constants,
and rates accepted by the Director of Engineering.
EFFECTIVE: October 1, 2021
29
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
WASTEWATER MAIN EXTENSION POLICY (Cont.)
Utility inspection fees shall be $50.00 per wastewater ERU.
The New Smyrna Beach Utilities requires in many cases, in addition to the contribution
provisions set forth herein, construction by the developer to provide for off-site extension
of water necessary to connect the applicant’s property with the then terminus of the water
facilities adequate in size to provide service as deemed appropriate by the Director of
Engineering.
Financing of payment of wastewater main extensions is available pursuant to the terms
and conditions listed below:
1. Financing shall be available to all individual residential customer
applicants.
2. A 12-month or 24-month financing period shall be utilized.
3. An annual interest rate of 2% above prime shall be used.
4. The customer must execute an agreement which states the wastewater
service will be terminated if the customer is in default of payments. All
payments previously made are non-refundable.
5. All payments must be accelerated and due in full prior to transfer of
ownership of the property.
6. A non-refundable administrative fee of $50.00 must be paid at the time of
application in order to reimburse the New Smyrna Beach Utilities for
services required to administer the records and financing process.
EFFECTIVE: October 1, 2021
30
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
RECLAIMED WATER RATE SCHEDULE
PRIMARY TIER RATE:
Meter Size
Minimum
Monthly Charge
Included Gallonage
(Per KG) In Minimum
Monthly Charge
Gallonage Charge
Per KG
Over Monthly Maximum
3/4"
$11.76
15
(0-15,000)
$2.35
(15,001 and Above)
1"
$29.40
45
(0-45,000)
$2.35
(45,001 and Above)
1-1/2"
$58.80
100
(0-100,000)
$2.35
(100,001 and Above)
Major Users
Meter Size
Minimum
Monthly Charge
Flow Charge Per KG
2"
$88.20
$0.36
3"
$88.20
$0.36
4"
$88.20
$0.36
6"
$88.20
$0.36
Definitions and requirements are as follows:
1. All user services must be metered.
2. Meter sizes 3/4" to 1-1/2" will always be given the highest priority on
reclaimed water availability.
3. Major users must provide a minimum of three (3) days of wet weather
storage for the minimum flow rate of 1,900 gallons/acre/day on an annual
average. Major users are defined as reclaimed water customers whose
anticipated capacity exceeds 100,000 gallons per day (gpd) and/or
requiring a 2" meter and above.
EFFECTIVE: October 1, 2021
31
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
RECLAIMED WATER RATE SCHEDULE (Cont.)
SECONDARY TIER RATE
The secondary tier rate structure will apply to major users at $19.15/acre/month.
Qualifications for this rate are as follows:
1. All user services must be metered.
2. Major user must provide a minimum of three (3) days of wet weather
storage for the minimum flow rate of 1,900 gallons/acre/day on an annual
average. Major users are defined as reclaimed water customers whose
anticipated capacity exceeds 100,000 gallons per day (gpd) and/or
requiring a 2" meter and above.
Restrictions for this rate are as follows:
1. New Smyrna Beach Utilities will deliver reclaimed water flow to the
primary tier rate users and reduce the flow to secondary tier rate users
during times of limited availability of reclaimed water.
2. The user must accept the minimum flow rate stipulated under the
secondary tier rate qualifications, adjusted for availability, or the account
will automatically be converted to the primary tier rate schedule. The user
must then meet the requirements of this level of service and may not
convert back to the second-tier level of service unless approval is granted
by New Smyrna Beach Utilities.
EFFECTIVE: October 1, 2021
32
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
RECLAIMED WATER METER SETTING CHARGES
Meter Size
(Inches)
Charges
3/4"
$400.00
1"
$450.00
1-1/2"
$850.00
2"
$950.00
3"
$6,000.00
4"
$7,000.00
All Reclaimed Water Meter Setting Installation Charges for 1-1/2" or larger that require
a street crossing or long service (long side service) will be determined by the New Smyrna
Beach Utilities Engineering Department and based on the recovery of cost of such
installation. Reclaimed Water Meter Setting Charges for all connections over 4" will be
determined by the New Smyrna Beach Utilities Engineering Department and based on
the recovery of cost of such installation.
EFFECTIVE: October 1, 2021
33
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
RECLAIMED WATER BACKFLOW PREVENTION CHARGES
Installation charges for residential and commercial customers requiring a dual check
valve are included in the Reclaimed Water Meter Setting Charges.
Backflow prevention charges for other than dual check valves will be determined by the
New Smyrna Beach Utilities Engineering Department and based on the recovery of the
cost of such installation.
EFFECTIVE: October 1, 2021
34
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
RECLAIMED WATER MAIN EXTENSION POLICY
Applications for an extension of the New Smyrna Beach Utilities reclaimed water system
shall be in writing stating the location, beginning and termination thereof, with plans and
specifications in triplicate attached where such plans and specifications are required.
Such written request shall be submitted to the Director of Engineering, approved by the
Director of Engineering and all terms and conditions relating to said extension shall be
made and executed by and between the applicant property owner and/or contractor and
the New Smyrna Beach Utilities.
No person shall use New Smyrna Beach Utilities reclaimed water services without first
making application in writing for service, receiving New Smyrna Beach Utilities
approval and paying all charges incident to the application. Applications shall be made
on forms provided by the New Smyrna Beach Utilities and requests for reclaimed water
by firms, partnerships, associations and corporations shall be tendered only by their duly
authorized agents with the official title of the agent shown on the application.
No free reclaimed water service shall be furnished or rendered to any person or to the
City, County, State or public agency or instrumentality. All utility service furnished to
the customer will be through New Smyrna Beach Utilities meters and may not be re-
metered for the purpose of selling or otherwise disposing of such service. In no case shall
a customer, except with the written consent of the New Smyrna Beach Utilities, extend
reclaimed water lines across streets, alleys, lanes, courts, property lines, avenues, or other
public thoroughfares or rights-of-way in order to furnish utility service for adjacent
property even though such adjacent property is owned by the same customer.
No unauthorized person, without prior written consent of the New Smyrna Beach Utilities
may tap any pipe or main belonging to the New Smyrna Beach Utilities. All unauthorized
connections shall be subject to discontinuance until full payment is made for such service,
including administrative costs, testing, etc.
All pipes, conduits or other component parts of service installed in or upon the premises
of a customer shall conform to New Smyrna Beach Utilities standards of type, quality,
quantity and regulations regarding installation. All on-site facilities must be maintained
by applicant according to New Smyrna Beach Utilities standards. Unauthorized alteration
or modification of an on-site utility service interconnection may result in immediate
termination of the affected service and repair or restoration at the applicant's cost.
Prior to the reclaimed water plans approval by the New Smyrna Beach Utilities and the
execution of reclaimed water system extension applications by the New Smyrna Beach
Utilities, the applicant shall be required to execute a Developer's Agreement which shall
be binding upon the applicant, its successors and assigns. Developer's Agreements may
not be assigned to subdivision parcels and/or lots.
EFFECTIVE: October 1, 2021
35
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
RECLAIMED WATER MAIN EXTENSION POLICY (Cont.)
The New Smyrna Beach Utilities requires contributions-in-aid-of-construction,
preferably through the installation of reclaimed water transmission facilities by the
applicant desiring system extension with title to such facilities being transferred to the
New Smyrna Beach Utilities when the installation has been completed.
Each applicant shall be responsible for design, installation, inspection and testing for the
complete reclaimed water distribution system (reclaimed water mains, valves, fittings,
services, hydrants and all appurtenances as shown upon the approved design plans for
such distribution system) located in the street or streets adjoining or within the boundaries
of the applicant's property. The applicant shall be responsible for the above and shall
dedicate the above at no cost to the New Smyrna Beach Utilities.
The design of reclaimed water facilities must be prepared by a registered Professional
Civil Engineer and shall be recognized by the New Smyrna Beach Utilities subject to the
approval of the Director of Engineering.
As a prerequisite to the construction of any reclaimed water system proposed to the New
Smyrna Beach Utilities system, the applicant shall agree to grant to the New Smyrna
Beach Utilities, without cost in a form satisfactory to the New Smyrna Beach Utilities,
such easements or rights-of-way corresponding with the installation of the proposed
facilities.
The New Smyrna Beach Utilities representative shall inspect the installation of all
reclaimed water facilities installed which are proposed to be transferred to the New
Smyrna Beach Utilities ownership. In addition, the New Smyrna Beach Utilities
representative shall be present at all testing of the component parts of the reclaimed water
system. The results of said testing shall be certified by the engineer of record. The
Director of Engineering or their representative will be notified three (3) days prior to
testing.
Reclaimed water facilities constructed prior to interconnection with the New Smyrna
Beach Utilities existing facilities shall be conveyed to the New Smyrna Beach Utilities
via Bill of Sale which shall be free of all liens and encumbrances. The New Smyrna
Beach Utilities will not accept transfer of consumer lines, plumber lines or consumers
installation located on the discharge side of the water meter or on the customer side of
the point of delivery of service. Said facilities will remain the maintenance responsibility
of the applicant or subsequent customers.
EFFECTIVE: October 1, 2021
36
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
RECLAIMED WATER MAIN EXTENSION POLICY (Cont.)
The New Smyrna Beach Utilities will not accept title to any component part of the
reclaimed water system constructed by the applicant until the Director of Engineering has
approved the construction of said lines, verified the inspection of the construction and
accepted the tests associated with the construction and disinfection of such facilities. The
applicant must keep accurate cost records of for all applicable reclaimed water facilities
and must submit these with the Bill of Sale.
Residential off-site reclaimed water system services in undeveloped areas include:
1. Temporary extensions less than 6-inches in diameter may be permitted on
a case-by-case basis based on public necessity. No New Smyrna Beach
Utilities participation, credits or other customer tie-ins will be allowed.
Fire protection is not included, and applicant must pay all prevailing rates,
fees and charges and is totally responsible for all costs associated with this
extension, including looping the system which is a requirement.
2. 6-inch Reclaimed Water Main Extensions - The main extensions from the
New Smyrna Beach Utilities system to the applicant’s on-site facilities is
required to be paid by the applicant.
3. 8-inch Diameter or Larger Reclaimed Water Main Extensions - If the
applicant requires a 6-inch reclaimed water main and oversizing is
required, the New Smyrna Beach Utilities may, in order to promote a
project also needed for other purposes, pay for the material cost of the
differential between a 6-inch and the larger diameter main.
Residential off-site reclaimed water system services in developed areas include:
1. The New Smyrna Beach Utilities shall provide three options for service
for developed areas. Those options include:
Customer Payment
Area Development Agreement
Water Special District (Assessment, Taxing or Otherwise)
EFFECTIVE: October 1, 2021
37
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
RECLAIMED WATER MAIN EXTENSION POLICY (Cont.)
2. The New Smyrna Beach Utilities shall construct the extension upon
collection of Capital Connection Fees and extension costs from one
hundred percent (100%) of those customers upon said extension. Each
extension will be reviewed for feasibility based on prudent engineering
standards.
The remainder of the policies for individual customers within undeveloped
areas apply.
3. An area development agreement would be considered the same as any
other Developer's Agreement.
4. Special districts, special assessments or special taxing may be instituted
within the New Smyrna Beach Utilities service area. These shall be
considered as a development and on-site and off-site costs shall be
required like any other applicant in an undeveloped area. The off-site
improvements and extensions shall be handled like those for water
facilities.
5. The customer shall pay all cost for 6-inch reclaimed water main
extensions.
Commercial off-site reclaimed water system services in undeveloped areas include:
1. Reclaimed water facilities extensions shall be in accordance with special
provisions of utility standards and shall be complied with in their entirety;
otherwise, the requirements shall be the same as for residential service.
Commercial off-site reclaimed water services in developed areas include:
1. Reclaimed water facilities extensions shall be in accordance with special
provisions of utility standards and shall be complied with in their entirety;
otherwise, the requirements shall be the same as for residential service.
Hydraulic share for reclaimed water mains is defined as follows:
1. 6" - 270 ERU's
2. 8" - 600 ERU's
3. 10" - 1,000 ERU's
4. 12" - 1,700 ERU's
5. 16" - 3,400 ERU's
EFFECTIVE: October 1, 2021
38
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
RECLAIMED WATER MAIN EXTENSION POLICY (Cont.)
Other calculations may be accepted by the Director of Engineering, if performed and
properly sealed by a Florida Licensed Professional Engineer, using constants, and rates
accepted by the Director of Engineering.
Utility inspection fees shall be $50.00 per reclaimed water Equivalent Residential Unit
(ERU).
The New Smyrna Beach Utilities requires in many cases, in addition to the contribution
provisions set forth herein, construction by the developer to provide for off-site extension
of reclaimed water necessary to connect the applicant’s property with the then terminus
of the reclaimed water facilities adequate in size to provide service as deemed appropriate
by the Director of Engineering.
Additional Infrastructure Needs - Any New Smyrna Beach Utilities utility infrastructure
needs will be considered separately.
Financing of payment of reclaimed main extensions is available pursuant to the terms
and conditions listed below:
1. Financing would be available to all individual residential customer
applicants.
2. A 12-month or 24-month financing period shall be utilized.
3. An annual interest rate of 2% above prime shall be used.
4. The customer must execute an agreement which states water will be
terminated if the customer is in default of payments. All payments
previously made are non-refundable.
5. All payments must be accelerated and due in full prior to transfer of
ownership of the property.
6. A non-refundable administrative fee of $50.00 must be paid at the time
of application in order to reimburse the New Smyrna Beach Utilities for
services required to administer the records and financing process.
EFFECTIVE: October 1, 2021
39
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
RECLAIMED WATER IRRIGATION POLICY
Existing water customers having irrigation meters in areas where reclaimed water is
available shall have one (1) year from the date of notice of availability to change their
irrigation service from potable water to reclaimed water.
The New Smyrna Beach Utilities will not provide new irrigation water (potable) service
in an area where reclaimed water service is available.
EFFECTIVE: October 1, 2021
40
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CUSTOMER DEPOSIT
I. REQUEST FOR UTILITY SERVICES
Application for utility services may be established by telephone, on-line or in person.
II. DEPOSIT
It is the policy of the New Smyrna Beach Utilities to require a deposit of all new
applicants for water, wastewater, and reclaimed water services as follows:
A. Water Service
The security deposit for each water account for the various meter sizes offered
is as follows:
5/8" $40.00
1" $100.00
1-1/2" $200.00
2" $500.00
3" $600.00
4" $1,000.00
6" $1,500.00
8" $2,000.00
B. Wastewater Service
The security deposit for each wastewater account for the various meter sizes
offered is as follows:
5/8" $70.00
1" $150.00
1-1/2" $300.00
2" $500.00
3" $600.00
4" $1,000.00
6" $1,500.00
8" $2,000.00
In the event wastewater service only is furnished by the New Smyrna Beach
Utilities and no water is connected to the system, the deposit for the account
will be determined by the New Smyrna Beach Utilities prior to providing
service.
EFFECTIVE: October 1, 2021
41
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CUSTOMER DEPOSIT (Cont.)
C. Reclaimed Water Service
The security deposit for each reclaimed service for the various service/meter
sizes offered is as follows:
3/4" $20.00
1" $100.00
1-1/2" $120.00
2" $200.00
3" $300.00
4" $400.00
6" $1,000.00
III.
DEPOSIT PAYMENTS
Residential Accounts
The customer will be billed for the deposit(s) and will have ten (10) days to pay
said deposit(s). If the customer does not pay the deposit(s) within the ten (10)
day period, utility services will automatically be disconnected.
Deposits must be made by cash, check, money order, or New Smyrna Beach
Utilities approved aid voucher. Credit cards will be accepted up to $1,000.00.
The following guidelines apply to all customers requesting residential water,
wastewater, and reclaimed services:
A. For existing accounts with good credit standing with the New Smyrna Beach
Utilities at the time of adoption of this policy, their existing deposits will
remain unchanged. Discontinuance of service for non-payment on existing
accounts will require an additional deposit.
B. Any new customer establishing services with the New Smyrna Beach
Utilities will have their social security number verified by the On-Line
Utility Exchange or any other provider of similar services. Based on the
results, the customer may or may not be required to pay a deposit.
EFFECTIVE: October 1, 2021
42
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CUSTOMER DEPOSIT (Cont.)
C. Any current or returning customer, with at least six (6) months of history
with the New Smyrna Beach Utilities requesting new service will have
their deposit based on current/previous account history. Customers with
no more than two late fees, no disconnections for non-payment, and no
returned checks, all within the most recent twenty-four (24) month period,
will not be required to pay a deposit. Any returning customers not
meeting these criteria will be required to pay a maximum deposit.
D. Any customer requesting service that has a paid write-off (final bill
balance sent to collections) with the New Smyrna Beach Utilities will be
required to pay the maximum deposit prior to connection of service. If the
customer has an unpaid write-off with the New Smyrna Beach Utilities,
they will be required to pay it in full, along with the maximum deposit
prior to connection of service.
E. The New Smyrna Beach Utilities will not transfer a deposit from one
individual to another individual. Transfers of deposit(s) from one address
to another address for the same individual will be made provided the
account balance at the currently served location is in a current
(outstanding balance is zero) status.
F. If a customer transfers their deposit to an account within the system, the
final bill on the old account, if delinquent, will be transferred to the current
account for collection and becomes subject to collections and disconnect
procedures.
G. Customers that are continuously delinquent are subject to update their
deposit.
EFFECTIVE: October 1, 2021
43
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CUSTOMER DEPOSIT (Cont.)
General Service (Commercial) Accounts
A. The customer will need to pay the full deposit at the time the account is
being established.
B. Deposit payments must be made by cash, check, or money order. Credit
cards will be accepted up to $1,000.
C. When the required combined total deposit exceeds $1,000, the applicant,
at their option, may furnish in lieu of cash the following instruments:
1. A surety bond for the full amount required.
OR
2. An irrevocable letter of credit satisfactory to the New Smyrna
Beach Utilities for the full amount required.
In the event the above instruments mature, the New Smyrna Beach
Utilities reserves the right to request cash (legal tender) for the required
deposit. Failure to comply with this requirement will result in
discontinuance of service.
D. For new accounts, the New Smyrna Beach Utilities will initiate a review
of customer’s monthly billings as compared to the deposit paid, not less
than six months but not more than one year from the service date.
EFFECTIVE: October 1, 2021
44
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CUSTOMER DEPOSIT (Cont.)
IV. ADDITIONAL DEPOSITS
In the event the utility service is discontinued for non-payment or has received
two (2) or more returned checks within a twelve (12) month period, the New
Smyrna Beach Utilities may require a deposit(s) sufficient to cover at least two
(2) months of the previous average monthly billing to be paid within ten (10) days
from notice. If such additional deposit is not made within ten (10) days, the New
Smyrna Beach Utilities may disconnect service in accordance with the collection
and disconnect policy. On a case-by-case basis, an extended due date for
additional deposits may be considered.
V. INTEREST ON CUSTOMER POLICY
Interest rate to be determined by the New Smyrna Beach Utilities each year and
will be credited to the customer's account each month beginning with the first full
month of service.
VI. REFUNDS OF DEPOSITS
For residential accounts only, the New Smyrna Beach Utilities will promptly and
automatically credit the deposit to the customer’s account after adoption date of
the policy when:
1. The customer had paid bills for the previous twenty-four (24)
consecutive residential billings without having service
disconnected for non-payment;
AND
2. Without having more than two (2) occasions on which a bill was
delinquent for the previous twenty-four (24) months;
AND
3. When a customer has not had any returned checks within a twenty-
four (24) month period (excludes verified bank errors).
The deposits are refundable only to the customer whose name appears thereon.
EFFECTIVE: October 1, 2021
45
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
CUSTOMER DEPOSIT (Cont.)
VII. RECORDS OF DEPOSIT
A. The New Smyrna Beach Utilities will keep records to show:
1. Name, address and Social Security number of each depositor.
2. Amount and date of deposit.
3. Each transaction concerning deposit.
B. The New Smyrna Beach Utilities will issue a receipt of deposit to each
applicant from whom a deposit is received and provide a means whereby
a depositor may establish claim if the receipt is lost.
C. A record of each unclaimed deposit will be maintained, and the New
Smyrna Beach Utilities will make a reasonable effort to return the deposit.
VIII. OTHER CHARGES
Late Charges
Utility accounts that have a past due balance of less than $25.00 will not be
assessed a late charge.
Accounts with a past due balance greater than $25.00 will be charged $5.00 or
1.5%, whichever is greater.
Returned Checks
If the customer pays the returned check before the check is received from the
bank, the fee is $20.00.
If the check has already been received from the bank, the fee is $35.00.
EFFECTIVE: October 1, 2021
46
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
SERVICE FEES SCHEDULE
The New Smyrna Beach Utilities shall charge and collect for customer service fees based
on the type of service rendered.
Availability
This schedule is available at any location within the New Smyrna Beach Utilities service
area in accordance with the service policies of the Commission.
Terms of Payment
Payment for services rendered shall be made at the time the service is requested.
Fees
The fees to be charged for services rendered are as follows:
SERVICE REQUESTS* FEES
(*For Water, Wastewater, and Reclaimed Water)
Service Requests will only be performed during regular working $ 35.00
hours. Requests received by 2:00 p.m. M-F will
be completed on the same day, requests received after 2:00 p.m. will
be completed no later than 2:00 p.m. the following business day.
Service Request After Hours Emergency Only Determined by $150.00
the New Smyrna Beach Utilities
Meter Lock Charge** $ 35.00
(**Required for meter sets for construction or as may be determined
needed by the New Smyrna Beach Utilities)
Temporary Cut-In/Cut-Out Service for Building Maintenance, $ 75.00
Etc. (Weekdays) (Requires 24 hrs. Notice; Services will be active from
11:00 a.m. the day of cut-in to 11:00 a.m. the next day.)
Temporary Cut-In/Cut-Out Service for Building Maintenance, $100.00
Etc. (Weekends) (Requires 24 hrs. Notice; Services will be active from
11:00 a.m. on Friday to 11:00 a.m. on Monday.)
EFFECTIVE: October 1, 2021
47
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
SERVICE FEES SCHEDULE (Cont.)
SERVICE REQUESTS FEES
Reconnection Fee After Disconnection for Non-Payment, $ 50.00
Regular Working Hours
Reconnection Fee After Unauthorized (Illegal) Connection* $150.00
(*Minimum or Actual Cost of Investigation)
Reconnection at Pole $150.00
Meter Reset Charge After Unauthorized (Illegal) Connection $150.00
(Same as Supplemental Meter)
TAMPERING FEES**
Cut Seal or Cut Lock Fee $ 35.00
Damaged Equipment $ 75.00
Meter Tampering / Unauthorized Use (Illegal) Fee*** - 1
st
Offense $300.00
(***Minimum Plus Any Applicable Service Charges)
Meter Tampering / Unauthorized Use (Illegal) Fee*** - Repeat
Occurrence (***Minimum Plus Any Applicable Service Charges) $500.00
Fire Hydrant Use / Unauthorized Use (Illegal) Fee*** $300.00
(***Minimum Plus Any Applicable Service Charges)
**Utility Tampering / and/or Unauthorized Use (Illegal) Fees and/or the Unauthorized Use of
Fire Hydrant will be assessed whenever there is evidence of meter tampering, meter
bypassing, self-restored services, or unauthorized use of fire hydrants. In addition to the cost
of investigation, repairs, the estimated usage, and other applicable service charges, up to and
including three times the estimated dollar value of the services obtained unlawfully.
Trip Fees: Any time a utility employee is deployed (other than routine meter readings or
maintenance) to a customer’s premise, whether for the process of disconnection (hang tag or
disconnect) or other services, the customer will bear the expense. New Smyrna Beach Utilities
personnel are not authorized to accept payment in the field. Residential energy audits are
exempt from trip fees.
Trip Fees During Regular Working Hours $ 35.00
Trip Fees After Hours Emergency Only* $150.00
(*Determined by the New Smyrna Beach Utilities)
EFFECTIVE: October 1, 2021
48
NEW SMYRNA BEACH UTILITIES
RATES, CHARGES AND FEES
SERVICE FEES SCHEDULE (Cont.)
SERVICE REQUESTS FEES
Research Fee: Per Each Request for Determination of Existing NSBU $ 20.00
Liens, Assessments and/or Promissory Notes
Collections Processing Fee: Customer’s Utility Account Sent to $ 35.00
Collections for Non-Payment Fee is
Per Account
2” Temporary Construction Meter – Equipment Fee: $750.00*
(*Portion Refundable Upon Return of Equipment)
The customer will pay the equipment fee upon receipt of the 2” temporary/portable meter.
Upon return of the meter in good working condition, the customer will receive a refund
of the lesser of $600 or this amount reduced by replacement cost of the damaged meter
and/or other components and reduced by the payment of final bill for usage. All
temporary/portable meters must be read, or usage reported monthly, and will be charged
a standard non-residential (commercial) water rate based on the meter size plus a non-
prorated $35 monthly processing fee. It is the responsibility of the customer to notify,
and upon New Smyrna Beach Utilities request, the location(s) of this meter.
2” Temporary Construction Meter Wrench Fee: $30.00**
(**Refundable upon Return of Equipment)
EFFECTIVE: October 1, 2021