8
In fact, the FAA test box and data recording system did physically have four thermocouples installed, but
the MPS needed to be revised to show the fourth thermocouple and explain its function. This thermocouple
reads the temperature at the tip to determine elapsed time between reaching activation temperature at the
discharge tip and initial discharge of the extinguishing agent. The MPS specifies a maximum elapsed time
of 60 seconds.
The thermocouple placement also affected the results. Elapsed time until discharge during tests number 12
and 13 became wildly excessive. The cause was determined when a different person installed the
thermocouple. In most of the tests, the FAA engineer had located the fourth thermocouple so that it was
almost touching the eutectic tips. Up to that point, we had received satisfactory results in our tests with all
bottles discharging within 60 seconds of reaching the activation temperature. In tests 12 and 13, a Boeing
DER located the thermocouple. These test times were longer than the required 60 seconds. These tests
were initially classified as failures. In the following tests where the FAA engineer located the thermocouple,
satisfactory results were again obtained. An investigation found that the Boeing DER had located the
thermocouple about 5/8 inch away from the tips. The closer location of the thermocouple gave a more
accurate reading of the temperature at the nozzle ends and we had to disqualify tests 12 and 13 due to an
inconsistency in thermocouple placement.
The remaining 15 tests went quickly and accurately when each person was delegated only a few tasks to
perform. The consistency of quality paper crumpling, thermocouple placement, time keeping, observations
and record keeping from test to test was important to the fairness to all participants. The delegation of
specific tasks ensured uniformity of test proceures.
Component Qualification/Certification Process
Once the suppliers have passed the tests per the MPS, the next step is for them to submit Drawings, an
Acceptance Test Procedure (ATP) and a Qualification Test Procedure (QTP) to Boeing for review and
comment/approval. Qualification tests include tests such as vibration tests, burst tests and corrosion
analysis. These tests will be used to qualify the bottle to the Boeing SCD. Compliance can be shown by
test, similarity to a previously tested part or by analysis.
A Boeing DER then reviews and approves these documents using a FAA form 8110-3 showing compliance
to the QTP. Then the QTP is reviewed with the FAA and a Request for Conformity (form 8120-10) is
submitted to the FAA by the relevant DER. The FAA arranges for conformity of the test parts and setup
and authorizes a test witness. The supplier then performs the testing per the QTP and reports failures
immediately to Boeing for disposition before proceeding. Once the testing has been successfully completed
a Qualification Test Report (QTR) is submitted to Boeing for review and comment/approval. Boeing
approves the QTR using an FAA form 8110-3 signed by the relevant DERs.
Installation Certification Process
Once the component has been qualified, Boeing then certifies the installations of the component in the
airplane per a Certification Test Plan (CTP). The CTP specifies that the testing will be accomplished in a
simulated lavatory waste receptacle using a procedure similar to the MPS. Boeing tests these bottles in a 3
cubic foot test box using the same orientation and nozzle position in which the lavatory supplier installs the
bottles on the airplane. Lavatory suppliers may install these bottles at different angles due to space
considerations and the orientation could make a difference in extinguisher performance. The current